1. Design and Construction Supervision of Chikoko Bay State House Access Road (1.3km): July 2019 – September 2019

2. Feasibility Sudy and Detailed Engineering Design Liwonde Matawale Road (53km): March 2019 – September 2019

3. Economic Feasibility Study and Detailed Engineering Design and Preparation of Tender Documentation for the Capacity Improvement of M005 Road (From Mzuzu High Court to Mzuzu State House) in Mzuzu City: July 2018 – September 2019

4. Feasibility Study and Detailed Engineering Design for the Upgrading of Chimwaza Trading Centre - Nambuma (S115/T344) Road in Dowa District (19km): February 2019 – July 2019

5. Detailed Engineering Design and Preparation of Tender documentation for the Construction of Thuchila bridge in Thyolo: April 2018 – July 2019

6. Construction Supervision Low Volume Sealed Roads:– Kasungu Town Access Roads 4.2km: June 2018 – June 2019

7. Normal Maintenance Supervision Contract 2018/19 (Northern Region).: June 2018 – June 2019

8. Supervision of Construction of Low Volume Sealed Roads (Linthipe-Lobi): June 2018 – June 2019

9. Feasibility Study and Detailed Design of the Upgrading of Ntcheu – Kasinje Road S134/T384 from earth to Low Volume Sealed Standard (48km): June 2018 – June 2019

10. Design Review of Nsipe Chingeni Liwonde M001/M008 55km: November 2018 – June 2019

11. Detailed Design and Construction Supervision of Liwonde - Mangochi Road Project: July 2017 – April 2019

12. Urgent and Emergency Works on Chipasula River along Chidzanja Road and Mchesi - Kawale Road in Lilongwe City: December 2018 – March 2019

13. Detailed Design of Dualisation of 18 - 49 Road: July 2018 – November 2018

14. Detailed Engineering Design of Area 18 interchange: November 2017 – July 2018

15. Design of Low Volume Sealed Roads:– Ntchisi – Malomo (M007) Road 5km, Linthipe – Lobi (S122) Road 5km. : July 2017 – June 2018

16. Detailed Design and Construction Supervision of Liwonde – Mangochi Road Project (80km): Aug 2015 – June 2018

17. Detailed Design and Construction Supervision of Mzuzu – Nkhata Bay Road Project (48km): January 2015 – December 2017

18. Supervision for Maintenance of Roads and Bridges for Northern Region: Aug 2016 – July 2017

19. Road Sector Designs Contract 2016/17. Design of Low Volume Sealed Roads:– Road, Zaka – Neno (T397) Road 26km,: June 2016 – July 2017

20. Construction Supervision Low Volume Sealed Roads:– Rumphi - Nyika Road (M014) 10km.: June 2016 – July 2017

21. Detailed Design and Construction Supervision of Access Roads in Lilongwe and Blantyre Cities (34km): August 2016 – June 2017

22. Detailed Design & Construction Supervision of Upgrading of Selected Roads in Mzuzu City Roads (10km): Jan 2016 – Feb 2017

23. Detailed Design of Dualisation of Kaunda – Chendawaka Road in Lilongwe City (24km): May 2016 – December 2016

Read More

Projects Carried Out

  • Project Experience
  • Roads Sector
  • Water Sector
  • Structures

Projects Carried Out

Pamodzi Consulting Limited has carried out a lot of projects in road infrastructure, water supply, irrigation and buildings.

A. Completed Projects

A. Roads Sector

1. Design and Construction Supervision of Chikoko Bay State House Access Road (1.3km): July 2019 – September 2019

2. Feasibility Sudy and Detailed Engineering Design Liwonde Matawale Road (53km): March 2019 – September 2019

3. Economic Feasibility Study and Detailed Engineering Design and Preparation of Tender Documentation for the Capacity Improvement of M005 Road (From Mzuzu High Court to Mzuzu State House) in Mzuzu City: July 2018 – September 2019

4. Detailed Engineering Design and Preparation of Tender documentation for the Construction of Thuchila bridge in Thyolo: April 2018 – July 2019

5. Feasibility Study and Detailed Engineering Design for the Upgrading of Chimwaza Trading Centre - Nambuma (S115/T344) Road in Dowa District (19km): February 2019 – July 2019

6. Design Review of Nsipe Chingeni Liwonde M001/M008 55km: November 2018 – June 2019

7. Construction Supervision Low Volume Sealed Roads:– Kasungu Town Access Roads 4.2km: June 2018 – June 2019

8. Normal Maintenance Supervision Contract 2018/19 (Northern Region).: June 2018 – June 2019

9. Supervision of Construction of Low Volume Sealed Roads (Linthipe-Lobi): June 2018 – June 2019

10. Feasibility Study and Detailed Design of the Upgrading of Ntcheu – Kasinje Road S134/T384 from earth to Low Volume Sealed Standard (48km): June 2018 – June 2019

11. Detailed Design and Construction Supervision of Liwonde - Mangochi Road Project: July 2017 – April 2019

12. Urgent and Emergency Works on Chipasula River along Chidzanja Road and Mchesi - Kawale Road in Lilongwe City: December 2018 – March 2019

13. Detailed Design of Dualisation of 18 - 49 Road: July 2018 – November 2018

14. Detailed Engineering Design of Area 18 interchange: November 2017 – July 2018

15. Design of Low Volume Sealed Roads:– Ntchisi – Malomo (M007) Road 5km, Linthipe – Lobi (S122) Road 5km. : July 2017 – June 2018

16. Detailed Design and Construction Supervision of Liwonde – Mangochi Road Project (80km): Aug 2015 – June 2018

17. Detailed Design and Construction Supervision of Mzuzu – Nkhata Bay Road Project (48km): January 2015 – December 2017

18. Supervision for Maintenance of Roads and Bridges for Northern Region: Aug 2016 – July 2017

19. Construction Supervision Low Volume Sealed Roads:– Rumphi - Nyika Road (M014) 10km.: June 2016 – July 2017

20. Road Sector Designs Contract 2016/17. Design of Low Volume Sealed Roads:– Road, Zaka – Neno (T397) Road 26km,: June 2016 – July 2017

21. Detailed Design and Construction Supervision of Access Roads in Lilongwe and Blantyre Cities (34km): August 2016 – June 2017

22. Detailed Design & Construction Supervision of Upgrading of Selected Roads in Mzuzu City Roads (10km): Jan 2016 – Feb 2017

23. Detailed Design of Dualisation of Kaunda – Chendawaka Road in Lilongwe City (24km): May 2016 – December 2016

B. Structures

1. Detailed Engineering Design and Preparation of Tender documentation for Dwangwa Weighbridge Station in Nkhotakota: July 2018 – June 2020

2. Detailed Design Construction Supervision for 3 storey office structure for Shire Basin Conservation Programme in Blantyre: April 2015 – December 2017

3. Construction Supervision of Brick Wall Fence for ADL in City Centre: October 2016 – January 2017


B. Completed Projects (Past Five Years)

A. Roads Projects

1. Supervision for Maintenance of Roads and Bridges for Northern Region: Aug 2015 – July 2016

2. Detailed Design Review and Construction Supervision of Jenda – Edingeni Road Lot 1 (15km): July 2013 – August 2016

3. Detailed Design of Dualisation of Area 18 - 49 Road in Lilongwe City (3.5km): June 2015 – December 2015

4. Detailed Design of Kawere - Mkanda Road in Mchinji District (10km): July 2015 – March 2016

5. Supervision for Maintenance of Roads and Bridges for Northern Region: Aug 2014 – July 2015

6. Supervision for Maintenance of Roads and Bridges for Central Region: July 2013 – July 2014

7. Supervision for Maintenance of Roads and Bridges for Southern Region: Aug 2011 – September 2012

8. Detailed Design and Construction Supervision of Area 27 Access Roads in Lilongwe City (18km): October 2010 – November 2011

9. Deatailed Engineering Design of Mangochi Town Roads (2.66km): September 2020 – December 2020

10. Ugrading of Area 25 - Nsungwi - Dzenza Road: April 2019 – December 2020

11. Economic Feasibility and Detailed Engineering Design and Preparation of Tender Documentation for the Capacity improvement of Kenyatta Road (4km) and Mzimba Street (3.9km) to Six Lanes: April 2019 – December 2020

12. Economic Feasibility and Detailed Engineering Design and Preparation of Tender Documentation for the Kamuzu Central Roundabout Interchange (58.5m) on Kenyatta Road to Mzimba Street and Lingadzi Bridge (46m) on Kenyatta Road: April 2019 – December 2020

13. Construction Supervision of Roads and Bridges to Selected Irrigation Schemes In Central and Southern Region: September 2020 – December 2020

14. Design Review and Construction Supervision of Upgrading of the first 19km of Lirangwe - Chingale -Machinga S139 and T401 Road to Bitumen Standard: April 2018 – December 2020

15. Detailed Engineering Design of Access Roads 44km in Njewa Farm: September 2020 – December 2020

16. Construction Supervision of Nkhotakota Dwangwa M005 Road (20.5km): April 2019 – September 2020

17. Design Review and Construction Supervision of Blantyre Bypass Road: August 2019 – September 2020

18. Construction Supervision of Limbe-Maselema to Chiradzulu Turnoff Road: September 2018 – August 2020

19. Construction Supervision of Roads and Bridges in Lilongwe Zone: July 2019 – June 2020

20. Construction Supervision of the Upgrading of Dowa Boma - Chezi M016 Road to Bitumen Standard (14.4km): April 2018 – April 2020

21. Detailed Design and Construction Supervision of Area 13, 16, and 32 Access Roads in Lilongwe City: April 2019 – March 2020

22. Detailed Engineering Design of Kalinyeke Road Toll Plaza: October 2019 – March 2020

23. Detailed Engineering Design of Access Roads to Power Stations - Tedzani (8km), Nkula (8km), (Wovwe (17.6km) and Kapichira (17km) (2017-2018): June 2017 – June 2018

24. Detailed Engineering Design for the Road Infrastructure Development of Limbe West 15.4 (Kanjedza) and Blantyre West 6.3 (Namiwawa) 21.7km: July 2016 – April 2017

B. Water and Sanitation Projects

1. Design Review and Construction Supervision of Neno Water Supply Project: May 2013 – November 2014

2. Sanitation Study, Preliminary Design and Preparation of Strategic Plans for Balaka, Mulanje and Mwanza Towns: April 2012 – September 2013

3. Preliminary Design of Seven Centres Water Supply Schemes: Kasiya, Nsaru, Nathenje, Ntaja, Msamala, Nkando and Malosa Centres: September 2010 – March 2011

C. Structures Projects

1. Detailed Design and Construction Supervision of Urban Infrastructure Project, Karonga Stadium, Rumphi Stadium, Nkhotakota Bus Depot, Neno Market, Chiradzulu DC Office and Mulanje Stadium: January 2014 – December 2016

2. Detailed Design and Construction Supervision of Ntcheu Bus Depot: August 2014 – July 2016

3. Detailed Design and Construction Supervision of Mangochi Multi Purpose Hall and Offices : April 2014 – September 2015

4. Detailed Design and Construction Supervision of Balaka, Mthandizi, Ulongwe and Phalula Project: May 2013 – November 2014

5. Construction of additional structures at Chimutu Primary School: September 2019 – April 2020


C. On Going Projects

A. Roads Projects

1. Design Review and Construction Supervision of Upgrading of the first 19km of Lirangwe - Chingale -Machinga S139 and T401 Road to Bitumen Standard: April 2018 – April 2020

2. Detailed Engineering Design and Construction Supervision of Access Roads to Power Stations - Tedzani (8km), Nkula (8km), (Wovwe (17.6km) and Kapichira (17km) (2017-2018): July 2017 – June 2020

3. Economic Feasibility and Detailed Engineering Design and Preparation of Tender Documentation for the Capacity improvement of Kenyatta Road to Mzimba Street : April 2019 – March 2020

4. Detailed Design and Construction Supervision of Area 13, 16, and 32 Access Roads: April 2019 – March 2020

5. Detailed Engineering Design and Construction Supervision for the Road Infrastructure Development of Limbe West 15.4 (Kanjedza) and Blantyre West 6.3 (Namiwawa) 21.7km: July 2016 – August 2020

6. Upgrading of Area 25 - Nsungwi - Dzenza Road: April 2019 – March 2020

7. Construction Supervision of the Upgrading of Dowa Boma - Chezi M016 Road to Bitumen Standard (14.4km): April 2018 – April 2020

8. Construction Supervision of Nkhotakota Dwangwa M005 Road (20.5km): April 2019 – September 2020

9. Construction Supervision of Roads and Bridges in Lilongwe Zone: July 2019 – June 2020

10. Detailed Engineering Design of Kalinyeka Road Toll Plaza: October 2019 – February 2020

11. Deatailed Engineering Design of Jenda Road Toll Plaza: January 2020 – March 2020

12. Design Revie and Construction Supervision of Blantyre Bypass Road: August 2019 – September 2022

13. Construction Supervision of Limbe-Maselema to Chiradzulu Turnoff Road: September 2018 – August 2021

14. Construction Supervision of Roads and Bridges in Zomba Zone: September 2020 – July 2021

15. Detailed Design and Construction Supervision of Area 44 Bridge at Kauma to Area 44 Road (64m Bridge, 6.8m carriage way, 1.5m pedestrian walkway and 1.5m shoulder bridge: 3 spans, total of `64m, on pile foundation and prestressed beams): November 2019 – June 2021

16. Construction Supervision for the Road Infrastructure Development of Limbe West 15.4 (Kanjedza) and Blantyre West 6.3 (Namiwawa) 21.7km: July 2020 – June 2021

B. Water Sector

1. Detailed Design and Construction Supervision for Water Distribution Network Rehabilitation and Expansion in Lilongwe City: July 2018 – June 2020

2. Design and Supervision of Rehabilitation of Water Supply and Sanitation Services at 3 No teacher Training Colleges.: July 2018 – June 2020

3. Detailed Design and Construction Supervision for Water Distribution Network Rehabilitation and Expansion, Transmission line (400km), 4 water tanks and 5 pumping stations in Lilongwe City: July 2018 – December 2021

4. Design and Supervision of Rehabilitation of Water Supply and Sanitation Services at 3 No teacher Training Colleges.: July 2019 – April 2021

C. Structures

1. Expansion of Infrastructure and Minor Rehabilitation Works at Sixty (60) Teaching Primary Schools in Malawi: July 2018 – June 2020

2. Construction of additional structures at Chimutu Primary School: September 2019 – April 2020

3. Expansion of Infrastructure and Minor Rehabilitation Works at Sixty (60) Teaching Primary Schools in Malawi: July 2018 – August 2021

Roads Sector

  • Ngabu-Bangula M1

    Rehabilitation Project (25Km) in the Southern Region of Malawi - 2013 - 2014 (Supervision).
  • Lilongwe Road

    Maintenance Project in the Central Region of Malawi - 2013 - 2014 (Supervision)
  • Jenda-Edingeni Road

    Upgrading Project to Class 1 Bitumen Standard (15Km) in the Northern Region of Malawi - 2013 - 2016 (Design and Supervision)
  • Mzuzu Road

    Maintenance project in the Northern Region of Malawi - 2014 - 2016 (Supervision)
  • Mzuzu-Nkhata-Bay M5 (46Km)

    Rehabilitation Project in the Northern Region of Malawi- 2016 - 2018 (Design and Supervision)
  • Area 18 roundabout to Kaunda road junction (3.2Km)

    in the Central Region of Malawi-2015 (Design)
  • Kawere-Mkanda Road (10Km)

    Upgrading Project in the Central Region of Malaw i- 2015 (Design)
  • Liwonde-Mangochi M3 (78Km)

    Rehabilitation Project in the Southern Region of Malaw i- 2015 - 2018 (Design and Supervision)
  • jalawe

    Jalawe Culvert-Rumphi District, on M1 Road

    <<Click here More Pictures on the Project>>

Water Sector

  • Neno Water Supply Project

    Design Review and Construction Supervision of Neno Water Supply Project in Southern Region of Malawi – May 2013 to November 2014
  • Songwe Water Supply Project

    Detailed Design of Songwe Water Supply Project in Karonga District in the Northern Region of Malawi – July 2009 to May 2010.
  • Likoma and Chizumulu Water Supply Projects

    Construction Supervision of Likoma and Chizumulu Water Supply Projects in Northern Region of Malawi – September 2009 toNovember 2010.

Structures

  • Shire River Basin Offices

    Design and Construction Supervision of Shire River Basin Offices in the Southern Region of Malawi – May 2015 to June 2017.